RMIW Act 10Chapter II · Preparation of Scheme
Section 10 · Draft scheme
Text size — level 1 of 4
(1)
The officer empowered by the State Government under section 8, shall submit a draft scheme to the State Government, and such scheme shall, so far as he deems necessary, embody the following particulars and be accompanied by the following documents, namely:-(a)
a specification and plan of the work which it is proposed to construct or maintain and an estimate of the capital or recurring expenditure involved thereby:(b)
the estimated time required for the completion of a scheme of construction:(c)
a statement detailing-(d)
the extent to which it will be necessary in his opinion to make compensation for damage caused to property by the carrying out of the scheme and the expenditure required for this purpose:(e)
the area which will be benefited by the scheme:(f)
the method of management of the work:(g)
with reference to section 19, the method or methods by which the State Government will be recouped or compensated for expenditure incurred by in:(h)
where all or any of the owners within the benefited area agree-(i)
the description of any river or stream flowing in a natural channel or of any lake or other natural collection of still water, whereof the water should be applied or used for the purpose of the work:(j)
any other matter which is required by the circumstances of the case.(2)
Such scheme shall also embody any particulars and be accompanied by any documents required by any rules made under section 49.(3)
Any agreement referred to in clause (h) of sub-section (1) may provide that on payment of the amount expressed therein, the work shall vest in and be maintained by the owners executing the agreement subject to the provisions of Part III.Your private note on this section