Section 89 · Result of applicant's failure to construct work or comply with conditions
Text size — level 1 of 4
(1)
If an applicant or his representative-in-interest fails-(a)
to construct the work for the purpose for which the land has been acquired under this Act; or(b)
to construct and maintain the necessary works in accordance with the conditions stated in sub-section (3) of Section 87 to the satisfaction of the Collector;(2)
An order of the Collector for the return of the land shall operate to re-vest the land in the person to whom it belonged before the acquisition or in his representative-in-interest, as the case may be, subject to all the rights of other person existing at the time of acquisition.Your private note on this section