MERC Regulations 49Chapter · Transmission
Section 49 · Norms for operation
Text size — level 1 of 4
- 49.1 Target availability for full recovery of annual transmission charges
Note 1 : Recovery of annual transmission charges below the level of target availability shall be on pro rata basis. At zero availability, no transmission charges shall be payable.Note 2 : - The target availability shall be calculated in accordance with procedure provided in the Annexure-II to these Regulations.
| (a) | AC system :- | 98 per cent |
| (b) | HVDC bi-pole links and HVDC back-to-back stations :- | 95 per cent |