- Where by any Sikkim law, any act or proceeding is directed or allowed to be done or taken in any Court or office on a certain day or within a specified period then if the Court or office is closed on that day on the last day of the specified period, the act or proceeding shall be considered as done or taken in due time if it is done or taken on the next day afterwards on which the Court or office is open.