धारा 36 · Charges for unscheduled interchange
अक्षर आकार — स्तर 1, कुल 4 में से
- 36.1 The generating station may be entitled to receive or shall be required to bear, as the case may be, the charges for deviations between energy sent-out corresponding to scheduled generation and actual energy sent-out, in accordance with the Balancing and Settlement Code, as may be published by the State Load Despatch Centre and approved by the Commission:Provided that the rate for determination of such charges shall be as notified by the Commission from time to time.